The works for the carabinase phase have been completed, work on the installations is continuing.
B2
Work is currently underway on the reinforced concrete structure. The building has reached level +2.
D4/C5
The base structures are finished and the erection of the reinforced concrete structure continues. The building is approaching the concreting of level 0.
C4
It is in the initial phase of works, it is expected that the erection of the carabinase structure will start in September.
B1/C2/C3
Works begin in September 2026, currently in the preparatory and infrastructure phases, in accordance with the project development schedule.
C1
D3
Infrastructure works will continue in accordance with the development plan and the defined construction phases of the project.